How Long Does a Website Project Take in the Philippines?
Eight to sixteen weeks for a standard site, and only six to nine are production. Where the time actually goes, and how to plan backwards from a launch date.
Hans Allí
Managing director & lead consultant·August 17, 2026

How Long Does a Website Project Take in the Philippines?
Somewhere in the first call, usually right after budget, the question arrives: how long will this take? It deserves a straight answer, so here is ours. For a standard company website, plan on eight to sixteen weeks from planning to launch. That is the range we quote in proposals, and it has held up across ten years of building websites.
Here is the part worth understanding: the hands-on production inside that calendar, discovery through build, usually adds up to six to nine working weeks. The rest is reviews, approvals, and content. The build is the predictable part; the calendar is really about decisions. What follows is where the weeks actually go, what stretches them, and how to plan backwards if you already have a date you cannot move.
Where the weeks actually go
A website project is four phases, and they overlap more than a neat diagram suggests. Here is how the calendar typically breaks down for a standard company site:
- Discovery and strategy, 2 to 3 weeks. Goals, audiences, sitemap, and a content plan. This phase feels slow because nothing visual exists yet, but it is where the site gets its shape. Projects that skip it pay for it later, usually in redesigned pages.
- Design, 2 to 4 weeks. Direction first, then the key pages, then the rest of the system. Each review round adds real calendar days, so the number of reviewers matters more than the number of pages.
- Build, 3 to 6 weeks. Responsive development, the CMS, forms, integrations, and the details that make a design work as a website. This is the phase clients worry about most and the one that surprises us least.
- Content load, QA, and launch, 1 to 3 weeks. Real content goes in, everything gets tested on real devices, and the launch itself gets a quiet buffer day or two.
Add them up and you get the eight to sixteen weeks we started with. The spread between the two ends is not mysterious: it is how quickly decisions come back and how ready the content is.
What makes projects run long
In our experience, three things stretch a website timeline, and none of them is the build.
Content is first, and it is not close. The classic stall goes like this: design is approved, the build is done, and then the site sits, finished, waiting for six paragraphs and a team photo. We have watched that wait run longer than the entire build phase. Writing about your own company is genuinely hard, and it always loses to the day job unless someone owns it early.
Approval loops are second. One reviewer who can decide turns a design round in two days. A committee of five turns it in two weeks, because each person's feedback has to be collected, reconciled, and sometimes refereed. Neither is wrong, but they belong on different timelines, and it helps everyone to say so at the start.
Scope drift is third. The mid-build "while we're at it" additions, a careers portal here, a members area there, each reasonable on its own. We flag these as they come, because saying yes quietly is how a fourteen-week project becomes a five-month one.
When we have missed a launch date, it usually traces back to one of these, and we own our share of it: more than once we have overestimated how much writing a client team can produce in a normal work week, and planned as if the day job would politely step aside.
Underneath all three sits a fact we plan around: our counterpart on the client side almost never has the website as their full-time job. They are a marketing manager, an operations head, a founder, fitting our requests between the work they were hired to do. Knowing that changes how we run projects: fewer and smaller asks with specific deadlines, materials requested early, and a schedule that leaves room for their real week. The timeline belongs to both teams, and it works best when it respects both calendars.
What makes projects run fast
The fast projects share a profile, and it has little to do with size:
- A decision-maker in the room. Someone who can say yes without convening a meeting. This single factor moves timelines more than any tool we use.
- Content handled early. Either the material exists before design starts, or a writer joins in week one and works alongside the design phase instead of after it.
- A mature platform. Building on Webflow or WordPress means the foundations are proven and the schedule carries less risk than custom-built everything.
- An existing brand system. When the logo, colors, and voice are settled, design starts from solid ground and the first review round goes quickly.
A project with all four lands near the eight-week end. A project with none of them makes sixteen look optimistic, no matter what the proposal says.
How timelines change by project type
The eight-to-sixteen-week figure covers the standard company site. Other builds run on different clocks:
- Basic or campaign site: 4 to 6 weeks. Few pages, one message, often a hard deadline. These move fast because the deadline forces the decisions.
- Standard company website: 8 to 16 weeks. The five-to-fifteen-page site most businesses need, from planning to launch.
- Content-heavy or multi-stakeholder site: 4 to 6 months. Schools, institutions, and organizations where many departments hold a piece of the content. The extra time is coordination, not construction.
- Ecommerce or custom development: 3 to 6 months. Product catalogs, payments, and custom features add build time and, more importantly, testing time.
One more thing worth saying: a redesign is not automatically faster than a new site. The design and build phases are the same, and migrating years of existing content often takes longer than writing fresh pages.
But AI can build a website in a day, right?
Honestly, yes. Give a modern AI tool a prompt and you will have a working site by dinner, and we say that without irony: AI is part of our own production now, and it is a real reason build weeks keep getting shorter. Our range has tightened along with the tools.
Notice what got faster, though: layout, boilerplate, first drafts, scaffolding. Useful starting points, and we use them as exactly that. The weeks in our range were never typing time. They are design judgment, accessibility, performance, and testing on real devices, plus everything no tool has compressed: deciding what the site should say about your organization, photography that looks like you, content from a team with day jobs, five stakeholders agreeing. A one-day site is a draft. A site that has to represent a real organization and convert its visitors has a different definition of done, and the distance between the two is where both the weeks and the craft live.
Planning backwards from a launch date
If you have a fixed date, an event, a product launch, a school enrollment season, work the calendar in reverse. Take the date, subtract two weeks as buffer, then subtract the range for your project type, and plan against the top of the range, not the bottom. For a standard site aimed at a November launch, that means a signed go by early July, and it means the content conversation starts in the first week.
And when the math does not fit, the honest lever is scope. A phased launch, the pages that matter most going live on your date with the rest following in a planned second round, protects both the deadline and the quality of what ships. It is the option we reach for when a date is truly fixed, and it beats rushing a full site past QA every time.
The buffer is not padding. Launches attract surprises, a DNS delay, a late photo shoot, a final round of feedback, and the projects that land calmly are the ones that left room for them.
If you are budgeting alongside the calendar, our guides on what a website costs in the Philippines and what it costs to maintain one cover the peso side of the same planning conversation. And if you want to see how a project actually starts, here is what happens after you reach out.
Have a date in mind? The earlier we hear it, the more of the calendar we can protect. Talk to us and bring the deadline; we plan better with it on the table.
How Fast Is Your Website, Really? What We Found When We Measured Ours
Our own homepage passed a layout shift check it should have failed. What website speed actually measures, why a good score can still mislead you, and the numbers from our own site this week.
Is Your Website Accessible? What Philippine Organizations Need to Know in 2026
What web accessibility means, what Philippine law requires (and for whom), which WCAG level to ask for, and a fifteen-minute check for your own site.
Does Your Website Comply With the Data Privacy Act? (We Checked Ours)
Before publishing a guide to the Data Privacy Act, we ran the checks against our own site first. What RA 10173 asks of a website, who has to register with the National Privacy Commission, and what implementing real consent actually takes.
What Goes in a Website Brief? A Guide for Philippine Businesses
A good brief gets you sharper proposals and comparable quotes. The eight things to include, three things to leave out, and a one-page template you can copy.
Related Posts
How to Choose a Web Design Company in the Philippines: A Buyer's Checklist
Three quotes for the same website can range from ₱60,000 to ₱450,000. Here is how we would read them: what each includes, who actually does the work, whether your team can run the site after launch, and which price fits.
How Fast Is Your Website, Really? What We Found When We Measured Ours
Our own homepage passed a layout shift check it should have failed. What website speed actually measures, why a good score can still mislead you, and the numbers from our own site this week.
Is Your Website Accessible? What Philippine Organizations Need to Know in 2026
What web accessibility means, what Philippine law requires (and for whom), which WCAG level to ask for, and a fifteen-minute check for your own site.
Does Your Website Comply With the Data Privacy Act? (We Checked Ours)
Before publishing a guide to the Data Privacy Act, we ran the checks against our own site first. What RA 10173 asks of a website, who has to register with the National Privacy Commission, and what implementing real consent actually takes.
What Goes in a Website Brief? A Guide for Philippine Businesses
A good brief gets you sharper proposals and comparable quotes. The eight things to include, three things to leave out, and a one-page template you can copy.
Who Owns Your Website? A Checklist for Philippine Businesses
Paying for a website and owning it are not the same thing. Seven accounts to check, how companies end up locked out, and a short message to send your vendor.
What does it actually cost to maintain a website in the Philippines?
Hosting renews at four and a half times the advertised rate, plugin flaws get attacked within hours, and SSL certificates now expire twice a year. Here is the honest annual cost of a Philippine business website, priced on the stack we actually run.
What makes a great business website? Lessons from 10 years of professional web design
After a decade of building websites for Philippine businesses, here are the timeless principles we've learned about what separates great business websites from forgettable ones.
Projects
We've planned, designed, and built 500+ websites for Philippine organizations.
.avif)
Co-founders Imat Marasigan, Hans Allí, and Mon Baldonado
About Dthree Digital
A decade building for the country's institutions
We are a web design and development consultancy based in Manila. We work in the space between branding agencies, ad agencies, and enterprise development shops. For ten years and more than 500 projects, the country's institutions, enterprises, and growing brands have trusted us with work that matters to them. Senior people lead every engagement and see it through design, build, and support. We stay accountable long after launch.








Let's build your next website, together.
Tell us what you're building. We'll bring senior people and a decade of experience to it.






